here's where we are as of december 6th...
- roofs are on
- windows are in
- siding is about 50%
- solar power plant components are being delivered or picked up this week
- door and lockset are in
- thanks Beattie Locksmiths
- lofts are built
- bathroom is framed
- rough plumbing happens this week
- thanks Gary Gibb of Gary's plumbing...
- thanks A-1 Builders for plumbing fixtures and coutertops...
- rough electrical starts saturday the 9th
- thanks jeffrey utter...
- air-sealing and insulation begins december 16th
- sheetrock to start xmess weekend